HS2 engineers have moved a 1,631tonne steel bridge into place over Lawley Middleway in Birmingham, part of Birmingham’s ring road, four days ahead of schedule. The work forms part of the UK’s HS2, high speed rail project and the operation was successfully delivered by Balfour Beatty VINCI and bridge move contractor Mammoet.
To minimise disruption to road users, the 112m span was moved during a series of night-time road closures, moving 18-24m every night using a special skidding system, ensuring that the road has remained open during the day.
Georgios Markakis, Project Manager at Balfour Beatty VINCI said: “This is a proud moment for my team, who have worked hard to deliver this impressive feat of engineering. Through careful planning and expert support from our supply chain, we were able to deliver the operation much quicker than planned.
HS2’s Head of Delivery for the Curzon Approaches, Greg Sugden said: “This is a fantastic achievement for the team, and the culmination of two years’ work including detailed design, planning, construction and delivery of this highly technical launch operation.
“Not only have we successfully delivered a milestone feat of engineering on the HS2 project, we’ve also been able to get the road back to normal early – which is good news for everyone.”
Over the following four nights, a skidding system – with a jacking push/pull mechanism, was used alongside the SPMTs to move the structure into place across Lawley Middleway. This combination of techniques is rarely used and is a first for Balfour Beatty VINCI on the HS2 project.
Lawley Middleway bridge forms part of the railway’s approach to Birmingham, with high-speed trains travelling out of the west portal of the 3.5 mile Bromford Tunnel at Washwood Heath and onto a one mile stretch of five connected viaducts – Duddeston Junction, Curzon 1, Curzon 2, Lawley Middleway and Curzon 3 which links onto the platforms of Birmingham Curzon Street Station.
Now at peak productivity, work will progress on this section of the railway with the second Bromford Tunnel breakthrough, Curzon 2 viaduct move, first Duddeston Junction Viaduct move, reopening of Aston Church Road, demolition of the old Aston Church Road bridge and start of construction of the new Saltley Viaduct – all set to happen over the next 12 months