• About
  • Advertise
  • Contact
Thursday, July 16, 2026
Newsletter
Global Highways
  • News
  • Products
  • Features
  • Categories
    • Asphalt Milling, Paving & Compaction
    • Concrete Milling, Paving & Compaction
    • Connected Construction
    • Earthmoving & Soil Compaction
    • Engines, Components & Tyres
    • Finance & Funding
    • Highway & Network Management
    • Maintenance
    • Materials
    • Recycling
    • Road Markings, Barriers & Workzone Protection
    • Road Structures
  • Events
    • Events Calendar
    • CONEXPO-CON/AGG 2026
    • Intertraffic Amsterdam 2026
    • bauma 2025
  • Latest Magazine
  • Videos
No Results
View All Results
  • News
  • Products
  • Features
  • Categories
    • Asphalt Milling, Paving & Compaction
    • Concrete Milling, Paving & Compaction
    • Connected Construction
    • Earthmoving & Soil Compaction
    • Engines, Components & Tyres
    • Finance & Funding
    • Highway & Network Management
    • Maintenance
    • Materials
    • Recycling
    • Road Markings, Barriers & Workzone Protection
    • Road Structures
  • Events
    • Events Calendar
    • CONEXPO-CON/AGG 2026
    • Intertraffic Amsterdam 2026
    • bauma 2025
  • Latest Magazine
  • Videos
No Results
View All Results
Home Features Complete control of machines using technology

Complete control of machines using technology

Sophisticated machine control technology has been utilised on heavy equipment to help deliver a challenging project in New Zealand

by Sarah Biswell
December 12, 2019
in Features
Reading Time: 4 mins read
A A
ITY_9Nfg[3].jpg

Without the novel solution, the contractor would have had to shut down the power lines

The contractor used a GPS-enabled in-cab crane location and warning system to avoid power lines located above a bridge. The firm used a combination of 3D models and dual mast receivers to track and map crane boom, jib and body within 30mm accuracy to ensure the safety of construction personnel.

Built to demanding specifications, the Transmission Gully motorway project is complex, with difficult and steep terrain requiring large-scale earthworks during construction. In all, 25 new structures totalling more than 1km are being built along the route. The largest of these, the Cannons Creek Bridge, is 230m long and reaches a height of 60m above the valley floor.

The $850 million Transmission Gully motorway is being delivered as a PPP by Wellington Gateway Partnership in partnership with the New Zealand Government. A key part of the Wellington Northern Corridor, the project is one of the most important stretches of new road in the North Island. When complete the Cannons Creek Bridge will be 24.5m wide, carrying two lanes in either direction and will require the use of 10,000m3 of concrete. A total of 44 steel girders, each 1.8m wide and 3m deep, make up the framework of the bridge deck, supported by two abutments and two piers.

However, the roadway and bridge lie below high voltage power lines. The contractor opted for incremental launching to install bridge girder assemblies over the open space between the piers. The sections are assembled in the launch yard and then moved onto rockers to be slid onto the piers. The project uses cranes in the launch yard, and in close proximity to high voltage power lines. Per regulations, contractors are required to stay outside a 10m exclusion zone during normal lifts and 6m during critical lifts. To keep the team safe, CPB HEB JV CP needed an innovative solution.

“We thought we might use a spotter on the ground but that wasn’t going to give us the assured reliability, particularly in the high winds that are common in Wellington,” said the JV’s survey manager. “We needed a way to relay immediate information to the crane operator. There was no off-the-shelf solution that we could find.”

Familiar with Trimble 3D machine control systems for earthmovers, the CPB HEB JV looked to Paul Miller, general manager at SITECH New Zealand in Auckland, New Zealand and Trimble for help. The two came up with a solution combining 3D modeling, Trimble Marine Construction Software and crane-mounted GPS.

lquEQgDA[2].jpg
Without the novel solution, the contractor would have had to shut down the power lines

To ensure safety, CPB HEB JV worked with Transpower New Zealand to develop a 3D model of the power lines and the envelope around the overhead transmission lines. The model simulated sway or sag of the power lines in varying wind and temperature conditions. The crane company also provided a 3D model of its machine, including all elements that could potentially contact the overhead lines.

“Once the essential elements were modeled, we were able to define an exclusion zone based on extreme conditions of the overhead power lines, as well as the crane’s maximum boom height above the cab,” said CPB HEB JV’s survey manager. “With that model and the associated algorithm, we had a real-time solution.”

Initially, one crawler crane was equipped with dual mast GPS receivers, one on the back of the crane cab and one on the top, with sensors added to the main boom. Inside the cab, a touchscreen provides a 3D view of the crane boom as it moves and its virtual proximity to the closest powerline exclusion zone. The algorithms in the program continually adjust the 3D visualisation by using real-time kinematic (RTK) GPS, mapping position and orientation of the crane boom to around 30mm accuracy. Before critical lifts, the survey team carried out testing to confirm that the coordinates of the GPS antenna on the boom tip matched the coordinates measured by the surveyor. The in-built custom alarms available in the Trimble Marine Construction (TMC) software were configured to provide progressive alerts.

“We did a lot of field testing to verify the alarm operations and to check issues related to losing satellite lock, particularly at the bottom of the gully,” added the survey manager. “But we never had a problem and the alarm system worked extraordinarily well.”

Soon after, the CPB HEB JV team installed the GPS-enabled crane location solution on a second crane.

Work on the Cannons Creek bridge began in 2018 and will be complete in early 2020. Completion of the Transmission Gully project is on track and scheduled for 2020.

• All images courtesy of Mark Coote Photography

Categories: Connected Construction
Promoted Content Header
Trimble Sitech

Related Posts

One of the tasks involved flipping bottles up from the ground (Image: Hitachi Construction Machinery Europe/HCME)

Europe’s best operators get ready for the LANDCROS Operator Challenge Final

by Sarah Biswell
July 10, 2026

More than 90 of Europe's most skilled excavator operators have showcased their skills in recent months by taking part in...

Road repairs work

The importance of road maintenance

by Staff Writer
July 10, 2026

Gülay Malkoc discusses the importance of investing in road maintenance.

The new 24litre engine from DEUTZ is designed for high-load genset applications - (image: Deutz)

High power generation from Deutz

by Mike Woof
July 8, 2026

Deutz is offering a rugged new engine to suit challenging power generation installations

Join our newsletter

The mission of Global Highways is to cover the latest technologies and best practices in all areas of road, bridge and tunnel construction and maintenance, as well as their safe operation and management.

Subscribe to our newsletter

About Us

  • About Us
  • Advertise
  • Contact
  • Terms & Conditions
  • Privacy Collection Notice
  • Privacy Policy

Popular Topics

  • News
  • Features
  • Products
  • Videos
  • Events
  • CONEXPO-CON/AGG 2026
  • Intertraffic Amsterdam 2026
  • bauma 2025

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited

No Results
View All Results
NEWSLETTER
  • News
  • Products
  • Features
  • Categories
    • Asphalt Milling, Paving & Compaction
    • Concrete Milling, Paving & Compaction
    • Connected Construction
    • Earthmoving & Soil Compaction
    • Engines, Components & Tyres
    • Finance & Funding
    • Highway & Network Management
    • Maintenance
    • Materials
    • Recycling
    • Road Markings, Barriers & Workzone Protection
    • Road Structures
  • Events
    • Events Calendar
    • CONEXPO-CON/AGG
    • Intertraffic Amsterdam 2026
    • bauma 2022
  • Latest Magazine
  • Videos
  • About
  • Advertise
  • Contact

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited